We repaired a replaced a stormwater pipe and filled a sink hole formed on the Yonkers Road near the North Raleigh Boulevard intersection.This project was an emergency repair due to the severity and sink hole location.

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
Ardurra (Design), Carolina Civilworks (construction)

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Water

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

This phase is complete.

Lead Department:
Water

Complete

We completed construction to repair Yonkers Road! We installed a new concrete stormwater pipe to replace the failed 42 inch steel pipe and filled the sink hole. The road is reopened to traffic.

Lead Department:
Water

Schedule

DateActivity
Summer 2026Project Planning 
Summer 2026Project Design Started
Late Summer 2026Project Design Completed
Fall 2026Construction Started
Winter 2026Construction Completed