Old stormwater pipe at a structure on Alamance Drive

Stormwater

Alamance Drive Drainage Improvements

Improving Drainage and Reducing Flooding

This project will improve the stormwater pipes at a property on Alamance Drive and Alleghany Road which are in poor condition and causing flooding during heavy rainstorms. During this project, we will:

  • Redirect water flow on Alamance Drive
  • Replace and upsize the stormwater system under Alleghany Road

Project Details

 
Type:
Stormwater
Budget:
$5 million
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Jordan Pack
Engineer
jordan.pack@raleighnc.gov
919-996-4080

 
Lead Department:
Water

Subscribe

 

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

This phase is complete.

Lead Department:
Water

Construction

We completed the design in Fall 2026 and expect construction to begin Fall 2027.

Project Maps

Maps with project improvements and detours are provided below.

Lead Department:
Water

Schedule

DateActivity
Spring 2021Planning phase begins
Summer 2024Design phase begins
Summer 2025Public meeting
Fall 2026Design phase complete
Fall 2027Construction begins
Spring 2029Construction Complete